When the 30-year old wastewater treatment system servicing a Transportation Center located in the Eastern Townships, in Quebec, began to show signs of failure, it was time to look for an alternative solution or a replacement system. Due to the low density of population in the area, no centralized treatment system was available in the vicinity. Therefore, a full review of all possible options for the design and installation of a new onsite wastewater treatment system was required.
Project Snapshot
System Specifications: Replacement of a malfunctioning 30-year-old wastewater treatment system servicing a transportation center
Infiltrator Products Used: 336 Infiltrator Quick4® Standard chambers
Daily Flow: 1,585 US gallons per day